We’re committed to improving our ecosystems, quality of life, and communities for the better.
Our passion and commitment to the integration of innovative science and engineering drive us to exceed on behalf of every client.
The Horseshoe Mill Dam, built in 1827, served as the first barrier to fish passage on the Weweantic River in Wareham, Massachusetts. For over 150 years, migratory fish were unable to reach their breeding grounds upstream due to this structure. However, thanks to the efforts of the Buzzards Bay Coalition and its project partners, the dam was successfully removed between December 2019 and February 2021. As early as April 2021, migratory fish were seen swimming unimpeded from Buzzards Bay to lay their eggs in freshwater upstream. A true success story!
This blog explores the Horseshoe Mill Dam removal project and celebrates the significant milestone in the recovery of fish populations and the restoration of ecological processes in the Weweantic River.
The Weweantic River winds its way through the picturesque landscapes of southeastern Massachusetts, spanning a length of 17.0 miles. This land is the traditional territory of the Wampanoag/Wôpanâak tribes. Derived from the Wampanoag language, Weweantic means “crooked” or “wandering stream.”
Originating from the wetlands in Carver, the river flows in a southerly direction meandering through swampy birch and maple forests in Middleborough and Rochester. Eventually, it empties into a Buzzards Bay estuary near the mouth of the Sippican River in Wareham. The river’s watershed covers approximately 18,000 acres, with numerous cranberry bogs situated in its upper sections.
Although the Weweantic River historically teemed with fish, the presence of the Horseshoe Mill Dam posed an obstacle to fish passage. The dam, spanning the Weweantic River at the head-of-tide, was built in 1827 to support a metal forge mill. Although it was once part of the infrastructure that supported Wareham’s economy, it had been decommissioned and left crumbling for decades. The defunct dam restricted to tidal inundation, hindered the migration of important fish species, and impacted riverine ecological processes.
The Weweantic River is the largest tributary to Buzzards Bay and provides 20 percent of all freshwater flow into Buzzards Bay. The meeting of salinity and nutrients through the tidal flow creates a vibrant ecosystem. It supports diverse communities of wetland species and a variety of non-migratory and migratory fish species, including river herring, white perch, and American eel. It is also home to the southernmost population of rainbow smelt in the United States, marking a significant change from a century ago when rainbow smelt were found as far south as the Chesapeake Bay. In the 1960s, smelt populations were even present in the Hudson River in New York.
Further highlighting the ecological significance of the Weweantic River and its surrounding watershed are the unique tidal freshwater wetland plant communities. The wetland areas surrounding the Horseshoe Mill Dam site contained two rare wetland plants, Parker’s Pipewort (Eriocaulon parkeri) and Pygmyweed (Crassula aquatica), both of which are designated as priority habitats for rare species.
Additionally, situated along the shore of Buzzards Bay and the Weweantic River is the Cromeset Neck & Mark’s Cove Marsh Wildlife Sanctuary. The 47-acre wildlife sanctuary consists of three separate parcels within one mile of each other. Salt marsh comprises most of the wildlife sanctuary, and the property also contains approximately six contiguous acres of coastal woodland.
The Horseshoe Mill Dam removal project involved several phases to achieve its restoration goals.
An inspection of the dam, conducted in 2009, rated its condition as unsatisfactory and noted significant concrete deterioration and erosion. The dam also included a former concrete-walled mill race that was in a state of disrepair, with collapsed walls and obstructed channels. The Buzzards Bay Coalition acquired the 10-acre Horseshoe Mill Dam property in 2012 to preserve it, provide public access, and pursue river restoration.
In 2016, the Buzzards Bay Coalition contracted Princeton Hydro to provide an Alternatives Analysis for the Weweantic River restoration project and a Fish Passage Feasibility Study for the dam. The analysis included a thorough site investigation, historical data review, sediment evaluation, hydrologic and hydraulic analysis, and ecological assessment. The five options considered in the analysis were:
The analysis ultimately helped the Buzzards Bay Coalition determine that a complete dam removal offered the most favorable ecological and economic outcomes.
Princeton Hydro, contracted by the Buzzards Bay Coalition, provided site investigation, engineering design, permitting, and construction oversight services for the dam removal. With funding from the Bouchard 120 Natural Resource Damage Trustee Council and collaboration with various agencies, including the U.S. Fish and Wildlife Service and NOAA, the dam removal commenced in December 2019 and was successfully completed in early 2021. Just months later in April 2021, for the first time in 150+ years, migratory fish were once again spotted swimming unimpeded from Buzzards Bay to lay their eggs in freshwater upstream.
Since the completion of the dam removal, Buzzards Bay Coalition Restoration Ecologist Sara da Silva Quintal has been consistently visiting the site and monitoring the positive changes taking place. Her observations include vegetation changes, signs of migratory fish spawning, and the geomorphic evolution of the landscape. She shared a series of Nearmap images that demonstrate how the landscape is positively adjusting to the barrier removal:
The completion of the Horseshoe Mill Dam removal project marks a significant achievement in the restoration of fish passage and the preservation of ecological function in the Weweantic River. Through the collaborative efforts of the Buzzards Bay Coalition, government agencies, and project partners, migratory fish can now freely swim upstream to their breeding grounds.
The restoration effort rejuvenated more than three miles of the Weweantic River and restored migratory fish passage. The dam removal enhanced riverine, wetland, and tidal habitat critical to a diverse group of aquatic, wildlife and plant species. It allowed for the natural extension of upriver habitat for two rare tidal plant species, ensuring their long-term survival. The restoration work also enhanced public access to the area by increasing walking trails and constructing canoe/kayak launches, promoting recreational opportunities, and fostering a deeper connection between people and the river.
In an article written by Kasey Silvia in November 2021, the Vice President for Watershed Protection at Buzzards Bay Coalition, Brendan Annett, was quoted as saying, “Removing this dam has immediately improved the natural functions of the Weweantic, undoing many years of environmental damage and it has already begun to bring the river back to life.”
The success of this project serves as a testament to the importance of collaborative conservation efforts in safeguarding and restoring our natural resources.
Princeton Hydro is a leader in dam removal in the Northeast, having designed and removed 80 dams. To view additional dam removal projects that we have completed, click here. For more information on our dam removal services, contact us here.
add comment
Yes, I would like to receive Princeton Hydro's quarterly newsletter and occasional email updates. Sign me up!
Δ
Your Full Name * Phone Number * Your Email * Organization Address Message *
By EmailBy Phone
Submit
Couldn’t find a match? Check back often as we post new positions throughout the year.